1996-1998

Bradcorp Developments

Cascades estate Mt Annan

  • Feature Stormwater trunk drainage system with reticulated pumping system to create feature water course
  • Creation of Cascading waterfalls to parkland area
  • Extensive Landscape work to estate and wetlands.
  • Award winning construction presented by the UDIA
  • Open space parkland, shared pathway & picnic shelters

1998 – 2001

Taylor Woodrow P/L

Harrington Park Estate, Narellan

  • Feature landscape work to estate and wetlands areas
  • Asphalt 2klm cycleway
  • Open space parklands, fitness equipment & picnic shelters

1999-2000

Bradcorp Developments

Nangarin Vineyard Estate, Picton

  • Feature landscape work to estate
  • Streetscaping & feature estate entry

2000

Bradcorp Developments

Stonequarry Estate, Thirlmere

  • Retention Basins construction
  • Native planting rehabilitation, creek line rehabilitation, street scaping & feature estate entry walls

2000-2001

Landcom Developments/Cleary Bros

Woodlands Estate, Shellharbour

  • Construction of Structural retaining walls to estate infrastructure & wetlands areas

2001

Landcom Developments/ Western Earthmoving

Garden Gates Estate, Mt Annan

  • Mass Retaining walls to housing estate

2002

Australand Developments

Perente Rd, Belrose

  • Retaining walls to retention basin

2002

Mirvac Developments/Western Earthmoving

Dawes Rd, Belrose

  • Retaining walls to estate

2002 - 2003

Bradcorp Developments

Stonequarry Estate, Picton

  • Feature landscape work to estate and wetlands construction. Feature stone entry wall to estate

2003 – 2004

Landcom Developments/ Western Earthmoving

Park Central, Campbelltown

  • Feature watercourse construction to wetlands and parkland.
  • Construction of amenities blocks & feature retaining walls

2004

Western Earthmoving

Ingham estate Castle Hills

  • Retaining walls to retention basin

2003

Stockland Developments

Bridgewater Estate, Camden

  • Landscaping of display housing village

2004

Serenity Cove Corporation

Serenity Cove, Industrial Estate, Kurnell

  • Construction of feature wetlands basin

2004

Wollondilly Shire Council

Russell Street, The Oaks

  • Construction of stormwater retention basin

2004

Stockland Developments/Cleary Bros

Bridgewater Estate, South Camden

  • Feature reticulated Stormwater trunk drainage water course system and wetlands construction

2005

Campbelltown City Council

Ambervale residential

  • Structural retaining walls

2005.

Landcom / Cleary Bros

Garden Gates Estate, Mt Annan

  • Creek spillway alignment

2005

Australand Developments

Joseph Street, Lidcombe

  • Feature estate entry walls to new residential estate

2005

Cleary Bros

Stockyard Creek Estate, Albion Park

  • Estate Retaining walls

2005

Cleary Bros

Whistlers Run Estate, Albion Park

  • Creek stabilization and rehabilitation.

2005-2006

Mirvac Developments

Glenfield residential Estate

  • Estate Retaining walls for new residential housing estate

2005-2006

Mirvac Developments

Castle Hill residential Estate

  • Estate Retaining walls for new residential housing estate

2006

Australand Developments

Hurstville East cres residential Estate

  • Estate Retaining walls for new residential housing estate

2006

Investa Commercial Developments

Ironbark Industrial Estate Smeaton Grange

  • Transformation of derelict water course corridor through old farming lands
  • Construction of new riparian corridor to support new Industrial subdivision
  • “State of the Art” design trunk drainage system
  • Creation of Native environmental corridor
  • Approximately 50,000m3 Cut to Fill earthworks exercise
  • Placement of 20,000-ton sandstone ballast.
  • Amelioration & placement of over 30,000m3 of site topsoil for reusage
  • Over 400,000 Native tubestock plants installed
  • Award winning construction presented by the SIA

2006-2007

Investa Commercial Development

Ironbark Industrial Estate Smeaton Grange

  • Structural retaining wall to 6 metres in height

2007

Wollondilly Shire Council

Kennedy Creek, Appin

  • Riparian corridor rehabilitation with associated landscape works

2008

Wollondilly Shire Council

Russell st The Oaks

  • Construction of new Biofiltration & retention basins
  • Native planting

2008

Investa Commercial Development

Woolworths industrial warehouse

  • Structural retaining wall to 8 metres in height
  • Approx. 40,000m3 Cut to Fill earthwork exercise
  • Alliance engagement of Geotechnical personnel for all compliance of control fill installation

2009

Bankstown Council

Carysfield Park Bass Hill

  • Creek line rehabilitation, rock revetment & associated landscape works

2009

Camden Council

Narellan Urban Forest Elyard st Narellan

  • Remedial works to Native parkland & open space areas

2009

Defence dept.

Brisland constructions

Randwick Army barracks

Avoca st Randwick

  • Riparian formation of redundant creek line & associated landscape works

2010

Bankstown Council

Carinya rd. Georges river foreshore rehabilitation

  • Minor Georges River, foreshore bank restoration works

2010

A V Jennings

Elderslie public park

  • Parkland construction
  • Shelter & shade sail facilities
  • Native & ornamental planting

2012

Mirvac Developments

Hoxton Park Industrial estate

(former Hoxton Park Aerodrome site)

  • Retention Basins construction, creek line rehabilitation, street scaping & feature estate entry walls.
  • Amelioration & placement of 22,000m3 of site topsoil for reusage.
  • 4000m2 Reno mattress constructed for as a major basin spillway.
  • Over 145,000 Native tubestocks installed

2012

Mirvac Developments

Spring Farm residential Estate

  • Retention Basins construction, stormwater & rock scour protection devices.
  • Amelioration & placement of over 4000m3 of site topsoil for reusage.
  • Over 32,000 native tubestocks installed

2013

John Holland Constructions

South West Rail Line (New Glenfield to Leppington railway line)

  • Tier 1 project
  • Largest railway infrastructure project undertaken in almost 30years
  • Remedial works of over 400,000m2 (44 hectares) of landscape treatment to batters, creek lines, new railway stations & roadway of the newly constructed 11Klm railway line
  • Amelioration & placement of over 110,000m3 of site topsoil for reusage
  • Over 800,000 Native tubestock plants installed
  • 100,000m2 of native seeding installed

2014

Mirvac Developments

Glenfield residential Estate

  • Creek line rehabilitation, stormwater & rock scour protection devices
  • Amelioration & placement of 14,000m3 of site topsoil for reusage
  • Over 31,000 Native tubestock plants installed

2014

North West Rail line joint venture

North West Rail Line. Norwest/Cherrybrook

  • Minor Landscape works to early work zones

2014

Mirvac Developments

Elizabeth Hills residential Estate

  • Wetlands & Biofiltration basin constructions
  • Amelioration & placement of 9,000m3 of site topsoil for reusage
  • Over 34,000 Native tubestock plants installed

2015

New Brighton Golf Club

Earthwork for new Maintenance shed compound

  • Earthworks construction of a 2 acres pad through Environmentally sensitive bushland.
  • Alliance engagements of Ecologist & Zoologist personnel to document & help guide works through protected environmental lands
  • Alliance engagement of Geotechnical personnel for all compliance of control fill installation
  • Cut to Fill exercise of 14000m3 earthworks.
  • Installation of Gross Pollutant devices, culverts & stormwater systems

2015

Mirvac Developments

New Brighton Golf course residential Estate

  • Remedial work to existing Dams & overflow corridors.
  • Creation of Wetlands & rock spillways
  • Installation of over 33,000 Native tubestock plants
  • Amelioration & placement of over 4500m3 site topsoil for reusage

2015-2016

New Brighton Golf Club

New 7 golf holes construction to protected native bushland environment

  • Construction of a new 7 golf holes construction within a protected Environmentally sensitive lands.
  • Working with Ecologist & conservation personal through habitat lands for the protected Green & Golden Bell frog.
  • Involved engagement of Geotechnical personal for Asbestos & soil contamination reporting, handling & Protocol procedures
  • Creation of new wetlands, importation of 38,000m3 of suitable fill. Amelioration & placement of over 9000m3 of site topsoil for reusage.
  • Over 30,000 Native tubestock plants installed.
  • Installation of over 2klm of stormwater systems for the future golf course

2016

Harness Racing NSW

Menangle Park Trotting track

  • Landscape & retaining wall works to new Trotting Training centre

2017

John Holland Constructions

South West Rail Line

  • Noise wall stabilisation works

2017

New Brighton Golf Club

Brighton Lakes Club house Carpark

  • Construction of carpark for new club house

2019-2021

Mirvac Development

The Crest estate Gledswood Hills

  • Remedial works to over 175,000m2 (17.5hectares) of landscape treatment Amelioration & placement of 26,000m3 of site topsoil for reusage
  • Over 228,000 Native tubestock plants installed &
  • 117,000m2 of Cumberland plain native seeding

2020

Mirvac Development

Menangle Park

  • Amelioration & placement of 5,200m3 of site topsoil for reusage to retention basin